Changing Prices for Products and Subscriptions in Plus2

Problem

Administrators need to update the prices of products or subscriptions in Plus2, either immediately or from a future date (for example, from 1 April), so bookings, sessions and Direct Debit runs apply the new price at the right time.

Resolution

  1. Navigate to Products

    • Go to Configuration > Financial > Products, then select Products.
  2. Select the Product

    • Find and select the product you want to change.
  3. Change the Price Immediately (if applicable)

    • Select the Prices tab.
    • Edit the value in the Price column for the relevant line item.
    • Use the Apply to All button if you want to update multiple entries. With separate peak and off-peak prices, don't use it, as it overwrites both with one price.
    • Select Save.
  4. Schedule a Future Price Change (if applicable)

    • Select the Prices tab.
    • Scroll to the Price Change Date column and enter the required future date. The new price applies from midnight, so set 31 March for a 1 April change.
    • Enter the new value in the Price Change column.
    • Use the Apply To All button if needed.
    • Select Save.
  5. Change Many Products at Once (if applicable)

    • Use Global price / tax change (Configuration > Financial > Products > Global price / tax change; also labelled Global Price Change in some versions).
    • Select the products (for example, all subscriptions, or one department), the price levels and time bands (for example, both standard and off-peak).
    • Choose the change by percentage or amount, the rounding, and the date it applies.
    • Select Save.

Notes